2019-09-26

Erection of an entire Power Supply STWR 021

Application deadline: 2019-11-15

Erection of a power supply for the new coal loading (KV 116 and optional KV 117) and the necessary track infrastructure of the new STWR 021

scope:

  • erection of the power supply STWR 021
  • erection of power supply, driving support station, sand filling station
  • erection of track lighting (loading tracks, sidings)
  • erection of general lighting
  • erection of railway switch heatings and power supply for railway switches
  • erection of OSE systems for remote-controlled mast switches

The construction period is planned from 2021 to 2022 (optional 2023). Commissioning takes place according to current planning status in 2 stages (KV 116: Q III 2022 / Option KV 117: Q III 2023).

tender planned: March 2020

awarding scheduled: February 2021

Contact person

Frank Kleinau

Purchaser

0049 355 2887 2977